Reznor R6GI Unit Installation Manual Bedienungsanleitung Seite 9

  • Herunterladen
  • Zu meinen Handbüchern hinzufügen
  • Drucken
  • Seite
    / 40
  • Inhaltsverzeichnis
  • LESEZEICHEN
  • Bewertet. / 5. Basierend auf Kundenbewertungen
Seitenansicht 8
9
Unconditioned Spaces
All duct work passing through unconditioned space must
be properly insulated to minimize duct losses and prevent
condensation. Use insulation with an outer vapor barrier.
Refer to local codes for insulation material requirements.
Acoustical Duct Work
Certain installations may require the use of acoustical
lining inside the supply duct work.
• Acousticalinsulationmustbeinaccordancewiththe
current revision of the Sheet Metal and Air Conditioning
Contractors National Association (SMACNA) application
standard for duct liners.
• DuctliningmustbeULclassiedbattsorblanketswith
a fire hazard classification of FHC-25/50 or less.
• Fiberductworkmaybeusedinplaceofinternalduct
liners if the fiber duct work is in accordance with the
current revision of the SMACNA construction standard
on fibrous glass ducts. Fibrous duct work and internal
acoustical lining must be NFPA Class 1 air ducts when
tested per UL Standard 181 for Class 1 ducts.
UNIT INSTALLATION
Packaging Removal
Remove the shipping carton and User’s Manual from the
equipment. Take care not to damage the coil or cabinet
when removing the carton. For rooftop installations, remove
and discard the two supports attached beneath the unit.
Rigging & Hoisting
WARNING:
Toavoidtheriskofpropertydamage,personal
injury, or death, it is the rigger’s responsibility
to ensure that whatever means are used to hoist
theunitaresafeandadequate:
• The lifting equipment must be adequate for
theload.RefertoTable 11, (page 26)forunit
weights.
• Theunitmustbeliftedfromtheholesinthe
base rails using cables or chains.
• Spreaderbarsarerequiredtoprotecttheunit
and ensure even loading.
• Keeptheunitinanuprightpositionatalltimes.
The rigging must be located outside the units
centerofgravity.RefertoFigure 10 (page 26)
& Figure 11 (page 29)
forlocatingthecenter
ofgravity.
• Allpanelsmustbesecurelyinplaceduring
rigging and hoisting.
Clearances to Combustible Materials
These units are certified as combination heating and
cooling equipment for outdoor rooftop or ground level
installations. Units may be installed on combustible
flooring or Class A, B, or C roofing material when used
with bottom supply and return air ducts as long as the
followingrequirementsaremet:
Figure 3
2”
Figure 3. Ground Level Installation
• Ifusingbottomdischargewithreturnairductsaroof
curb must be installed prior to unit installation. See
Rigging and Hoisting section for setting of the unit.
• Sufcientclearanceforunobstructedairowthroughthe
outdoor coil must also be maintained in order to achieve
rated performance. For information about locating the
equipment, see page 5.
Ground Level
Ground level installations must be located according to
localbuildingcodesorordinancesandtheserequirements:
• Clearancesmustbeinaccordancewiththoseshown
in Figure 1 (page 5).
• Asuitablemountingpad(Figure 3) must be provided
and be separate from the building foundation. The pad
must be level to ensure proper condensate disposal and
strong enough to support the unit’s weight. The slab
height must be a minimum of 2” (5cm) above grade
and with adequate drainage.
• RemoveanddiscardthehorizontalSupplyandReturn
duct covers located on the rear of the unit. Form duct
attachment flanges by bending the sheet metal outward
90 degrees along the perforated lines.
• Firmly attachductwork directly to these angeswith
screws or other approved mechanical connections and
not to the Supply/Return air panels to avoid damage to
internal components of the equipment. Once completed
use approved duct sealing methods to ensure an air
and watertight seal is achieved.
Rooftop
Rooftop installations must be located according to local
buildingcodesorordinancesandtheserequirements:
• Theroofmustbecapableofhandlingtheweightofthe
unit. Reinforce the roof if necessary For unit weights,
see Table 11, (page 26).
• Theappropriateaccessoryroofcurbmustbeinstalled
prior to unit installation. The roof curb must be square
and level to ensure proper condensate drainage. See
Figure 4 (page 10). Please follow all instructions
provided with the kit.
• Secure roof curb or frame to roof using acceptable
mechanical methods per local codes. NOTE: Make sure
the two supports beneath the unit have been removed.
Seitenansicht 8
1 2 3 4 5 6 7 8 9 10 11 12 13 14 ... 39 40

Kommentare zu diesen Handbüchern

Keine Kommentare